清水混凝土剪力墙以及采用爬模施工的混凝土剪力墙在施工时,通常要求混凝土墙先于楼面梁板施工。当楼面梁采用钢筋混凝土梁时,目前采用植筋或预留钢筋接驳件的方式。该方式存在施工复杂、质量难以保障、新旧混凝土结合面不可靠等缺陷。介绍了一种新的钢筋混凝土剪力墙与后浇筑的钢筋混凝土梁的贯通式节点:通过在混凝土墙预留洞口并在洞内预留暗柱钢筋及墙体水平筋、洞口内壁凿毛等手段,保证了后浇筑混凝土梁与剪力墙之间节点的可靠性。静力试验和数值模拟结果表明,本节点的力学性能与整浇节点十分接近,验证了本设计的可靠性和实用性。试件的试验结果和数值分析结果吻合度较高,可以印证各自的可靠性。
Abstract
During the construction of plain concrete shear walls and concrete shear walls constructed using climbing formwork, it is usually required that the concrete wall be constructed before the floor beams and slabs. When reinforced concrete beams are used for floor beams, the current method is to plant steel bars or reserve steel bar connectors. This method has defects such as complex construction, difficulty in ensuring quality, and unreliable interface between new and old concrete. This article introduces a new type of through joint between reinforced concrete shear walls and post poured reinforced concrete beams: by reserving openings in the concrete wall and reserving hidden column steel bars and wall horizontal bars inside the openings, and chiseling the inner wall of the openings, the reliability of the joint between the post poured concrete beams and shear walls is ensured. Through static tests and numerical simulation calculations, it has been proven that the mechanical properties of this node are very close to those of the cast-in-place node, and the reliability and practicality of this design have been verified. The test results of the specimen are in good agreement with the numerical analysis results, which can confirm their respective reliability.
关键词
新老混凝土 /
后浇筑 /
贯通式 /
梁墙节点 /
节点试验
{{custom_keyword}} /
Key words
old and new concrete /
post pouring /
penetrating joint /
beam wall joint /
joint test
{{custom_keyword}} /
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}
参考文献
[1] 中华人民共和国住房和城乡建设部.高层建筑混凝土结构技术规程:JGJ 3—2010[S].北京:中国建筑工业出版社,2010.
Ministry of Housing and Ruban-rural Development of the People's Republic of China. Technical specification for structures of tall building:JGJ 3—2010[S].Beijing: China Architecture and Building Press,2010.(in Chinese)
[2] 南作宾. 高层建筑清水混凝土墙体大模板施工技术[J].中国建材科技,2016,25(5):88-91.
NAN Zuobin.Large formwork construction technology of high rise building clear water concrete wall[J].China Building Materials Science & Technology,2016,25(5):88-91.(in Chinese)
[3] 胡凌华,赵亮亮.天目里项目结构工程与建筑设计的双向营造[J].建筑创作,2020(6):110-113.
HU Linghua,ZHAO Liangliang.The interactive construction of 0ōeli considering structural engineering and architectural design[J].Architecture Creation,2020(6):110-113.(in Chinese)
[4] 麦家儿,卢晓智,何冠鸿,等.钢板连接及接驳器连接的支撑-腰梁-地下连续墙节点力学性能试验研究[J].建筑结构,2021,51(24):88-91,130-135.
MAI Jia'er,LU Xiaozhi,HE Guanhong,et al.Experimental study on mechanical performance of joints of strut-waist beam-diaphragm wall joint connected by steel plate and mechanical coupler[J].Building Structure,2021,51(24):88-91,130-135.(in Chinese)
[5] 中华人民共和国住房和城乡建设部.混凝土结构设计规范:GB 50010—2010[S].北京:中国建筑工业出版社,2010.
Ministry of Housing and Ruban-rural Development of the People's Republic of China.Code for design of concrete structures:GB 50010—2010[S].Beijing:China Architecture and Building Press,2010.(in Chinese)
[6] 姚方宝,关群,王浦东.基于ABAQUS塑性损伤模型损伤因子的仿真分析[J].结构工程师,2019,35(5):76-81.
YAO Fangbao,GUAN Qun,WANG Pudong.Simulation analysis of damage factor based on ABAQUS damaged plasticity model[J].Structural Engineers,2019,35(5):76-81.(in Chinese)
[7] 丁发兴,余志武,欧进萍.混凝土单轴受力损伤本构模型[J].长安大学学报(自然科学版),2008(4):70-73.
DING Faxing,YU Zhiwu,OU Jinping.Damage constitutive model for concrete under uniaxial stress conditions[J]. Journal of Chang'an University (Natural Science Edition),2008(4):70-73.(in Chinese)
[8] 周剑. 预制混凝土空心模剪力墙应用技术研究[D].北京:清华大学,2016.
ZHOU Jian.Study on the application technology of shear walls with precast concrete hollow moulds[D].Beijing:Tsinghua University,2016.(in Chinese)
[9] 赵玉川,刘逸翱.高强新旧混凝土界面粘结应力数值分析[J].中国水运(下半月),2023,23(3):138-140.
ZHAO Yuchuan,LIU Yiao.Numerical analysis of interfacial bonding stress between high-strength new and old concrete[J].China Water Transport,2023,23(3):138-140.(in Chinese)
[10] 刘健. 新老混凝土粘结的力学性能研究[D].大连:大连理工大学,2000.
LIU Jian.Study on the mechanics performance adherence of young on old of concrete[D].Dalian:Dalian University of Technology,2000.(in Chinese)
[11] 张晓光,陈泽赳,刘星,等.新旧混凝土结合面抗剪性能现场试验研究[J].结构工程师,2010,26(6):70-75.
ZHANG Xiaoguang,CHEN Zhejiu,LIU Xing,et al.Field test study on shearing property of bonding interface between new and old concrete[J].Structural Engineers,2010,26(6):70-75.(in Chinese)